MOERI¡¯s Ice Model Basin
Recent exploration for natural resources and their transportation in the arctic regions and the increase of traffic through the NSR have stimulated new structural concepts and ships, model tests in an ice tank are the preferred evaluation tool.
MOERI ice tank currently is to the process of constructing for 2010 completion. The ice tank is the first ice tank in Korea to meet the increasing research and development challenges and opportunities arising from the recent demands. Icebreaker, oceanic structure and marine equipment can be tested in this facility. |
| |
Dimension & Characteristics
- Name of the facility : MOERI¡¯s Ice model Basin
- Term of the project : Jun, 2006 ~ May, 2010
Main dimensions
- Tank size : 42m(L) X 32m(B) X 2.5m(D)
- Towing carriage : X-Y type, 0.0 ~ 3.0 m/s speed
- Refrigeration system : -30¡ÆC temperature control
- Two cold rooms |
| |
Project scheme
¡¯06.06-¡¯07.05(1st year) : Preparation of the technical request specification, Preliminary design of the ice tank and towing carriage
¡¯07.06-¡¯08.05(2nd year) : Basic and Detail design of the ice tank & towing carriage and competitive biding
¡¯08.06-¡¯09.05(Present) : Construction of the ice tank and manufacture of the towing carriage
¡¯09.06-¡¯10.05(4th year ) : Installation of DAQ system, A trial operation, Sep-up the ice test and analysis methods |
| |
Main functions Ice performance test for icebreaker
- Ice conditions : Level & Brash ice, Pre-sawn, Ridge, etc.
- Main Function : Resistance, Propulsion, Maneuvering
Measurement of the ice load in model scale for arctic platforms
- Measurement of the ice load and iceberg impact
- Monitoring and estimation of the ice load
Technical support for the arctic engineering
- Performance test for an extremely low temperature materials, equipments and electronic goods etc.
- Certificate authority for arctic engineering |
| |
 |
| |
| |
|
|
|
|
|
|